Daily Diary of Industrial Training

This is the daily diary of industrial training, It contains the daily work done by me or under my supervision.

Daily Diary IT

DAILY DIARY INDUSTRIAL TRAINING

Daily diary 5th Feb 2016

It was the day my industrial begun and this day Manomav Engineers Pvt. Ltd. Has completed the design of foundation plan for the site I was assigned to at Thapar University. I was asked to review the design and check If there is any rectification that could be found.

Daily diary 6th Feb 2016

This day as well I was analyzing and studying the foundation plans of the site. Along with various plan of footing plans of Plinth beams was also provided today.

Daily diary 9th Feb 2016

As per the plans, Bhoomi Poojan of the site was to be done on 15th Feb 2016 and all the designs were to be completed at least one week before so that proper scheduling of all the activities can be done. Till 15th Feb 2016 then Project Management team at Manomav Engineers Pvt. Ltd got together with Interarch team and decided to plan various activities of the project. Due to very strict guidelines to complete the project by 31st July 2016 sharp project management team was supposed to plan all the activities well in detail and keep up everything well with that tight schedule.

Daily diary 10th Feb 2016

For project management, It was decided the Microsoft Project will be used and all the work shall be done on it. A team from DeeKay Buildcon was also called in for various queries regarding the delivery of material, labor and other resources. Project management team then started working on planning all the resources their allocations.

Daily diary 11th Feb 2016

Project management team was still working on making schedule Gantt Chart etc. for the project.

Daily diary 12th Feb 2016

It was an OFF day for Vasant Panchami but Project management team was still working on making schedule Gantt Chart etc. for the project.

Daily diary 13th Feb 2016

Project management team completed the scheduling of the whole project and came up with the complete schedule of the project as per its drawing plans and builder’s considerations.

Daily diary 15th Feb 2016

It was Bhoomi Poojan today, nothing special happened but I was introduced with the site engineers, project managers labor contractors etc.

Daily diary 16th Feb 2016

It was the first day on the site, the site was cleared already cleared by Thapar University so we were ready to do the survey.

Daily diary 17th Feb 2016

Today, marking on site was done as per the excavation plans and machines were called in for excavating.

Daily diary 18th Feb 2016

The excavation was going on today.

Daily diary 19th Feb 2016

The excavation was going on today as well.

Daily diary 22nd Feb 2016

The excavation was going on today as well.

Laying of PCC for foundation begun today for 12 columns

Daily diary 23rd Feb 2016

The excavation was going on today as well.

PCC for 12 more columns was laid.

Daily diary 24th Feb 2016

The excavation was going on today as well.

PCC for 12 more columns was laid.

Daily diary 25th Feb 2016

The excavation was completed today.

 PCC for 12 more columns was laid.

Daily diary 26th Feb 2016

PCC for 12 more columns was laid.

Daily diary 29th Feb 2016

PCC for 12 more columns was laid.

The footing of 8 RCC columns was prepared and completed.

Daily diary 1st Mar 2016

PCC for 12 more columns was laid.

12 more RCC footings were prepared.

Daily diary 2nd Mar 2016

PCC for 12 more columns was laid.

16 more RCC footings for columns were completed making a total of 36 columns footing ready.

Daily diary 3rd Mar 2016

PCC for 12 more columns was laid.

Laying of RCC column footings begun for 20 more.

Daily diary 4th, Mar 2016

PCC for all 132 columns was complete today. 16 more RCC footing were prepared.

Daily diary 7th, Mar 2016

20 RCC footings were completed today.

Daily diary 8th, Mar 2016

Today as well 20 RCC footing were prepared.

Daily diary 9th, Mar 2016

RCC footings for all 10 more columns were ready today.

Construction of 8 column’s pedestals was started and completed.

Daily diary 10th, Mar 2016

10 more RCC column’s footing were laid today completing footing for all 132 footings.

12 more columns pedestals were completed.

Daily diary 11th, Mar 2016

22 more RCC column’s pedestals were laid today.

Daily diary 14th, Mar 2016

22 more RCC column’s pedestals were laid today.

Daily diary 15th, Mar 2016

22 more RCC column’s pedestals were laid today.

Daily diary 16th, Mar 2016

22 more RCC column’s pedestals were laid today.

Daily diary 17th, Mar 2016

12 more RCC column’s pedestals were laid today.

Construction of 20 RCC Plinth beams begun.

Daily diary 18th, Mar 2016

With the construction of 12 more RCC column’s pedestals, all the columns were complete till J-bolt level.

20 more RCC Plinth level beams were completed

Daily diary 21st, Mar 2016

56 RCC plinth beams were completed today.

Diary of 22nd, Mar 2016

56 more RCC plinth beams were constructed.

Additional work for making the Tax variable in BSNL day to day maintenance work was assigned.

Diary  of 23rd, Mar 2016

OFF day for Shaheed Divas but still worked for Variable taxes

Diary of 24th, Mar 2016

OFF for Holi.

Worked for variable taxes

Dairy of 25th, Mar 2016

OFF day for Good Friday.

Completed and delivered additional assignment.

Dairy of 28th, Mar 2016

40 RCC plinth beams were constructed.

Filling of soil begun on the area where plinth beams were complete.

Dairy of 29th, Mar 2016

40 more RCC plinth beams were constructed.

Soil’s filling back was being done

30th, Mar 2016

With construction of 31 more plinth beams all were complete

Soil’s filling back was being done.

Brick work around the raised portion begun.

31st, Mar 2016

Soil’s filling back was being done.

Brick work was being done around the raised portion.

1st April 2016

Soil’s filling back was being done.

Brickwork was being done around the raised portion.

PCC layer on compacted portion started.

4th April 2016

Filling of soil was complete.

Brickwork was being done around the raised portion.

PCC layer was still being laid.

5th April 2016

Brickwork around the raised portion was complete.

PCC layer was still being laid.

Laying of RCC floor was started.

6th April 2016

Laying of PCC layer was complete.

Steel reinforcements for the floor were being tied.

7th April 2016

While steel reinforcements are being tied.

Concreting of floor started.

8th April 2016

While steel reinforcements are still being tied in some remaining portions.

Concreting of the floor was done in some other ready areas.

11th April 2016

RCC layer was still being laid.

12th April 2016

RCC layer was still being laid.

Assembling of steel column begun on site.

13th April 2016

RCC layer was still being laid.

Steel columns were being assembled.

14th April 2016

RCC layer was still being laid.

Steel columns were still being assembled.

15th April 2016

Laying RCC layer was complete for the ground floor.

Assembly of steel columns and beam began for area A1

18th April 2016

While some steel columns and beams were being assembled for area A1

19th April 2016

Assembling of Steel columns and beams began for area A1.

20th April 2016

Assembling of Steel columns and beams begun for area A2.

Erected the Steel Components for ground floor area A1.

21st April 2016

Assembling of Steel columns and beams begun for area A2.

Erected the Steel Components for ground floor area A1.

22nd April 2016

Assembling of Steel columns and beams begun for area A2.

Erected the Steel Components for ground floor area A2.

25th April 2016

Assembling of Steel columns and beams begun for area A3.

Erected the Steel Components for ground floor area A2.

26th April 2016

Assembling of Steel columns and beams begun for area A3.

Erected the Steel Components for ground floor area A2.

27th April 2016

Assembling of Steel columns and beams begun for area A3.

Erected the Steel Components for ground floor area A2.

28th April 2016

Assembling of Steel columns and beams begun for area A4.

Erected the Steel Components for ground floor area A3.

29th April 2016

Assembling of Steel columns and beams begun for area A4.

Erected the Steel Components for ground floor area A3.

 